Shanghai Electric Makes Significant Progress on the CSP Tower and Parabolic Trough Plant in Mohammed bin Rashid Al Maktoum Solar Park
PR90064
SHANGHAI, June 12, 2021 /PRNewswire=KYODO JBN/--
Shanghai Electric ("Shanghai Electric" or "the Company") (601727.SS and
02727.HK) announced that the first molten salt tank hydro test for the
Parabolic Trough Plant-II (PT2) of the fourth phase of Mohammed bin Rashid Al
Maktoum Solar Park was carried out on May 9, the positive results of which laid
a crucial foundation for the next phase of the molten salt system commission.
The test was followed by finalized molten salt pipeline installation inside the
Concentrated Solar Power (CSP) tower, marking another key milestone in
construction progress.
The fourth phase of Mohammed bin Rashid Al Maktoum Solar Park is the largest
single-site Concentrated Solar Power (CSP) project in the world, which uses
world-leading hybrid solar energy technologies to generate 950MW of clean
energy, including a 100 MW CSP tower plant, three 200 MW parabolic trough CSP
plants and 250 MW of photovoltaic (PV) capacity.
The solar tower, standing 260m-high at the center of the CSP tower plant site,
will also be the world's tallest structure of its kind. Upon completion, the
combined thermal energy storage of the solar tower and parabolic trough plants
will allow for 24/7 energy availability, with each parabolic trough CSP plant
possessing an energy storage capacity of 13.5 hours and the tower boasting up
to 15 hours.
Nitrate, the heat storage medium for the Parabolic Trough Plant-II, is stored
in eight tanks, with each one measuring 45 meters in diameter and 25,000 cubic
meters in capacity. The harsh desert environment presented a massive challenge
to the test, and labor shortages during Ramadan added another layer of
uncertainty to overall progress. The test was eventually completed on time with
the help of water trucks which transported and unloaded the water to
provisional water tanks, through which the water was pumped into the molten
salt tanks.
"I extend my appreciation to all the on-site workers for their dedication and
hard work to ensure the test was completed at speed and on time, despite the
tremendous difficulties caused by a labor shortage and local
high-temperatures," said Zhao Hui, Project Manager of Dubai CSP Project of
Shanghai Electric Power Generation Engineering Co.
"Their outstanding performance also guaranteed the smooth progress of the CSP
central tower pipeline installation, which is the core and one of the most
important parts of the structure. The space in the tower is extremely small,
given the total length of the central tower internal pipes is over 500 meters.
To make sure the work could be done on time, the project team formulated
well-thought-out installation plans and overcame all unseen problems without
causing any delay," he added.
The molten salt tank system is the answer to the challenges of thermal energy
storage. Thermal energy storage realized by molten salt systems enables power
generation on cloudy days, or long night after sunset, with high operating
efficiency and low capital costs per kilowatt-hour. During the daytime, the
molten salt is circulated to a heat exchanger from a cold tank to absorb heat
from the high-temperature oil. The heated molten salt can then be stored in an
insulated hot tank which can later send the liquid to power steam turbines at
night or during unfavourable weather conditions.
In 2018, Shanghai Electric was appointed as Engineering, Procurement and
Construction (EPC) contractor for the fourth phase of Mohammed bin Rashid Al
Maktoum Solar Park in Dubai after signing the agreement with DEWA (Dubai
Electricity and Water Authority) and ACWA Power to undertake both the 700 MW
CSP and 250 MW PV projects. Financed by China's Silk Fund and ACWA, it is a
landmark project of China's Belt and Road Initiative, as well as a significant
milestone of Shanghai Electric in participating in renewable energy utility
construction in the Middle East and its shift of focus from coal-fired energy
to renewables.
In 2021, Shanghai Electric ranks 17th in the list of top 100 international
contractors, 5th in the field of electric power engineering, according to the
latest evaluation released by the China International Contractors Association.
In addition, the Company has also been granted "A-level international
contractor", the highest rating, by the association.
Source:Shanghai Electric
Image Attachments Links:
Link: http://asianetnews.net/view-attachment?attach-id=393688
Caption: On-site workers celebrated the completion of the first molten salt tank hydro
test for the Parabolic Trough Plant-II (PT2) of the fourth phase of Mohammed
bin Rashid Al Maktoum Solar Park